   Guaranteed Service standard
 
   Interruption/Failure of Power Supply
  • In case of blown fuse from distribution mains/ service pole
    • Within 4 hours in towns and cities.
    • Within 8 Hours in rural areas.
  • In case of line break down:
    • Within 8 hours in towns and cities.
    • Within 48 hours in rural areas.
  • In case of distribution Transformer failure:
    • Within 24 hours in towns and cities
    • Within 72 hours in rural areas.
  • In case of major failure involving Power Transformers (33 KV and above):
    • Within 15 days. (Alternative supply to be restored as early as possible)
   Voltage Variation
  • Within 24 hours in case of local problems.
  • Within 3 months in case of inadequacy of LT distribution system.
  • Within 9 months in case of deficiency in the HT distribution system.
   Reconnection and disconnection if all formalities are complete - 24 hours
 
   New connection
  • If no new pole is required - within 7 days from receiving Offer cum bill for LT consumer
  • If new pole is needed - 30 days
 